While Associated Electric Cooperative continues to develop renewable power and energy efficiency measures as important
resources for meeting member systems' energy requirements, those resources will not be enough to meet members' growing
electricity needs. To ensure continued reliability, Associated is constructing the 540-megawatt Chouteau 2 combined-cycle
natural gas plant adjacent to its existing Chouteau Power Plant in the Mid-America Industrial Park, Pryor, Okla.
Combined-cycle plants are among the most efficient type of gas plants with very low emissions. These combined-cycle units
have greater efficiency than simple-cycle combustion turbine units because they employ both a steam turbine and a
combustion turbine to power the generators.
Emissions limits for the Chouteau 2 plant are among the strictest ever issued in the country for combined-cycle gas plants,
according to the air permit Associated received from the Oklahoma Department of Environmental Quality.
The U.S. Department of Agriculture Rural Utilities Service also issued July 24, 2009, a finding of no significant impact
(FONSI) for the Chouteau 2 plant, allowing the project to continue on schedule to meet members’ growing energy needs.
In conjunction with the power plant, a 33-mile gas pipeline is being constructed by Enogex LLC, which will provide gas
delivery services for the plant.
The Chouteau 2 project is on schedule to be complete mid-2011. Associated awarded the engineering, procurement and construction
contract to Kiewit-TIC, a joint venture between Kiewit Energy Co. and The Industrial Co.
|