Power plant recommissioning will deliver affordable capacity


       Associated’s recommissioning of its Unionville Power Plant, a 44-MW liquid fuel peaking facility in layup status since

       2014, will add capacity and also enhance fuel diversity. The ability to run on liquid fuel is valuable for generating
       electricity when natural gas is either expensive or undeliverable. The plant will be available starting in late 2023.





                                                                 System speeds restoration of
                                                                 major transmission line

                                                                   In December 2021, tornadoes brought down
                                                                 almost five miles of Associated’s West New
                                                                 Madrid-to-Dell 500-kilovolt line in southeast
                                                                 Missouri. Seventeen structures were destroyed
                                                                 with 10 of those towers suffering foundation
                                                                 damage. Six more towers sustained damage at
                                                                 conductor attachment points. Working together
                                                                 with M&A Electric Power Cooperative, one of
                                                                 Associated’s six member-owners, the transmis-
                                                                 sion structures and line went back in service
                                                                 June 1, 2022 – 30 days ahead of schedule.
                                                                 Construction included replacement of 17 towers,
                                                                 45 linear miles of conductor and 10 miles of
                                                                 steel static wire at a cost of $10 million. Disaster
                                                                 declaration reimbursements of 90% from the
                                                                 Federal Emergency Management Agency and
                                                                 up to 10% from the state of Missouri will cover
                                                                 much of the cost.